Trinity School, Sevenoaks

Client: Willmott Dixon Construction
Value: 2.7 million
Contract Period: 36 weeks
Completion: April 2016
Trinity School, Sevenoaks
Trinity School, Sevenoaks

A new secondary school was constructed in Sevenoaks on the site of the old Wildernesse School on Seal Hollow Road.

The existing school buildings were demolished and a new school with associated infrastructure constructed by Willmott Dixon Construction Ltd. Certain elements of the existing site were maintained, including the sports centre building, one MUGA pitch and a portion of the existing parking areas.

Gallagher was appointed by Willmott Dixon to undertake the:

  • Bulk Earthworks
  • Substructures
  • Waterproof RC Retaining Walls
  • Drainage
  • BWIC to Services
  • External Hard Landscaping works

Gallagher’s works were split over two phases - the groundworks and then the external works.

Our successful delivery of the St Augustine’s Academy in Maidstone and tough negotiations have resulted in the opportunity to work with and impress Willmott Dixon again.

Head Office address:
Gallagher Group, Leitrim House, Little Preston
Aylesford, Kent ME20 7NS

Telephone: 01622 716543
Email: info@gallagher-group.co.uk

Aggregates address:
Gallagher Aggregates Ltd., Hermitage Quarry
Hermitage Lane, Maidstone, Kent ME16 9NT

Telephone: 01622 726262
Email: quarry@gallagher-group.co.uk