1000 cu m of CONCRETE POURED IN 1 WEEK AT CORNWALLIS
November 2009
Early November has seen Gallagher place 1000 cubic metres of ready mixed concrete in the ground floor slab of the new academy building at the Cornwallis School in Maidstone in just one week.
All concrete was supplied by Gallagher Ready Mix from the Hermitage Quarry. The academy building is a £35m project being undertaken by Carillion Building Ltd, Gallagher is responsible for all foundations, drainage, roads, car parks and external works.