Building Expertise Case Studies - Monks Horton, Ashford

Horton Park Farm Phases 1&2, Monks Horton, Ashford

Phase 1:

Gallagher were appointed as the Principal Design and Build Contractor for the construction of this state of the art, organic farm facility for the raising of beef and lamb stock. The completed complex not only sets new standards for stock rearing, but also fully embraces the ‘green’ agenda we will all face in the future.

All works were carried out in a live farm environment, with over 30,000 cu m of spoil cut and filled to form the new site profiles. Timber clad steel framed buildings with clear spans in excess of 28 metres were then constructed to house cattle, store farm equipment, compost and silage. The contract included extensive areas of roads and hard standing together with all fitting out of bull pens and the like.

All farm effluent has been designed to be treated by passing through an extensive reed bed system constructed by Gallagher before discharging into a wetland bio diversity area. The design also ensured all rainwater run off from the roof area is collected into two 45,000 litre tanks for reuse in daily farm activities.

Gallagher’s involvement in Hermitage Farm and evident understanding of and affinity to the ways of farming was instrumental in being selected for the development and for then ensuring that the project was successfully completed to a high standard.

Phase 2:

Having successfully completed Phase 1 the team went on to be appointed to Design and Build Phase 2 of the project which included additional farm storage buildings along with new farm office buildings designed to resemble the existing farm complex which dated back to the 1800’s.

Whilst both the design and build met this requirement the modern interior office space benefits from generous natural day lighting with automated roof opening windows, under floor heating and in-ceiling cooling. This represents the first time in-ceiling cooling technology has been used in the UK. Once again the client’s ‘green’ agenda was addressed with all heated and chilled water being generated via a ground source heat pump connected to over 1200 metres of in ground pipe work.

In keeping with the setting of the development and to compliment this organic farms environmental commitment the team also erected in excess of 30 bat boxes and 5 owl boxes.

Client: Private
Value: £5 million
Contract Period:
Completion: December 2008

Download Case Study