Building Expertise Case Studies - Clipper Park, Tilbury

Clipper Park, Tilbury

Gallagher Contractors were employed as Principal Contractor under a design and build contract by Equity Estates. The project involved the construction of five separate blocks of industrial warehouse units providing 25 warehouse units totalling 77,000 sq ft.

The site was located on very poor alluvial grounds within the tidal zone of the River Thames and required extensive ground solutions including piling and innovative soil stabilisation techniques. Extensive surface water attenuation measures were also required.

The Gallagher team included Cornish Architects and Paul Owen Associates (Civil and Structural Engineering Consultant), both firms with whom Gallagher have carried out several design & build contracts.

Gallagher’s in-house civil engineering resources meant that a quick start was possible and that the site works progressed at speed and to a high standard – not an easy task with such poor ground conditions.

Client: Equity Estates Ltd
Value: £5.7 million
Contract Period: 37 weeks
Completion: June 2007

"We are very pleased with the completed scheme and we would like to work with you again in the future
"
Alastair Thomas
Managing Director, Equity Estates Ltd