Our new Gallaflo XS gets star billing at Maidstone TV studios

  • Gallaflo XS at the Maidstone Studios
  • Maidstone Studios 023
  • Wp 20150825 15 34 51 Pro

Maidstone TV Studios had a problem in that the floor surface in studio 5 had begun to deteriorate. This was beginning to impact on filming quality and that had been highlighted with the onset of High Definition cameras. Any deviation in the floor surface was magnified by the HD cameras. The issue was how to refurbish the studio floor with as little down time so as to not impact on filming up and coming productions.

Working with our binder provider Gypsol and working closely with the contractor EJS Flooring Solutions it was decided that Gallaflo XS flowing screed would be the best option. The speed of installation of the 1000m2 un-bonded screed would enable the 50 cubic metres of screed to be installed in one day. The ability to force dry the screed would enable the paint finish chosen to be used to be applied much quicker than other options considered.

We perfectly placed to meet the logistics plan to supply the 50 cubic metres of flowing screed required on the day of the pour. Gallagher supplied the screed in 7m3 per loads and ensured that there was a continuous supply of Gallaflo XS until the screeding was finished.

EJS Flooring Solutions finished the screeding on time and with a very high level quality finish, exceeding expectations.

Back to News Archive