Gallagher has secured an earthworks package from Lidl, as part of its construction of a new 20,000 square metre regional distribution centre in Northfleet, Kent.

Works commenced on 26th November and are proposed to be undertaken within twelve weeks.

Gallagher's works comprise:

  • General site clearance.
  • Large cut & fill exercise using site won & imported fill materials – 67,200m3.
  • Removal of unsuitable materials off-site.
  • The breaking-up of approximately 4,700m3 of reinforced concrete slabs, structures & roads and the subsequent crushing & screening on-site for re-use as a piling platform.
  • Civils works for the proposed new watermain.
  • Construction of piling platform & attendance to piling contractor.
  • Erection of new fencing.

Gallagher will be using a variety of plant and equipment from its own extensive fleet, ranging from 21 tonne capacity 360* excavators up to 52 tonne capacity. The crushing and screening plant have been supplied from Gallagher’s own aggregates equipment at Hermitage Quarry.